India’s first detention centre is being built in Goalpara district’s Matia.(ANI
In the final list of National Register of Final NRC status: 15 buildings, schools, hospital in India’s first detention centre for those not in Assam NRCCitizens (NRC) published on August 31, more than 19 lakh people were excluded. However, those left out can still apply to the designated Foreigners’ Tribunals within 120 days for their cases to be heard.
The work on India’s first detention centre is progressing at quick pace in Goalpara district’s West Matia area in Assam, weeks after the final National Register of Citizens (NRC) was published, leaving out nearly 1.9 million people.
“The work on this project started in December 2018, our target is to complete it by December 2019. It will cost around Rs 46 crore. Fifteen four-storey buildings are being built — 13 for men, 2 for women,” Junior Engineer (JE) of the detention centre, Rabin Das told ANI.
Some 1.9 million people found themselves out of the final version of the NRC published last month after years of efforts aimed at ending a four-decade movement against illegal immigrants. The Supreme Court-monitored process of updating the NRC for Assam, last compiled 68 years ago, took four years and 55,000 officials poring over 66.4 million documents.
Fifteen four-storey buildings are being built in the detention centre — 13 for men, 2 for women. ( ANI Photo )
Those left out have been given 120 days to approach the Foreigners’ Tribunals for review. Over 200 new tribunals have been set up across the state for this purpose. To accommodate the disenfranchised persons, temporary detention camps have been set up across the state. The one coming up in West Matia area is the country’s first formal detention centre
The detention centre is being constructed over an area of 2,88,000 square feet and will have separate residential facilities for the security personnel and officials. Das also stated that the centre will have separate toilets, hospital, kitchen, dining area, recreational area and a school.
“There will be buildings for officers grade 4 staff. It will have 2 security barracks. The water system will have a capacity of 50,000 litres,” he added, reports ANI.